The
Kentucky Transportation Cabinet (KYTC) District 5 Office says that there will be
lane closures on southbound KY 1747 (Hurstbourne Parkway) at the intersection
with Linn Station Road (mile point 12.2) beginning today at 9 a.m.
These lane closures will allow
for water main installation as part of the I-64/Hurstbourne Parkway interchange
improvement project. Southbound
Hurstbourne Parkway will be reduced to one lane at Linn Station Road 24 hours per day through 8:00 a.m. on Sunday, May 19.
Expect heavy delays on southbound Hurstbourne Parkway between US 60 and
Interstate 64 during this phase of construction. When possible, alternate
routes should be considered. MAC Construction and
Excavating of New Albany, Ind. was awarded a contract in the amount of $4.5
million. Work is scheduled for completion in late summer of 2013.