The
Kentucky Transportation Cabinet's District 5 Office announced a
ramp closure at the interchange of Interstates 64 and 264 this week.
Contract crews will be replacing concrete pavement on this ramp.
The
exit ramp from westbound I-264 (Watterson Expressway) to westbound I-64 (Exit
19B) is scheduled for closure from 7:00 p.m. tomorrow, July 17 until 4:00 p.m.
on Friday, July 19. Motorists should follow the signed detour via three
of the loop ramps in the I-264/I-64 interchange.
This
work is part of the I-264 construction project for concrete pavement repairs
between Browns Lane and Westport Road (mile points 18.4 to 20.7). Hall
Contracting, Inc. was awarded the contract for this project in the amount of
$8.1 million. The contract completion date is July 31, 2013.
The actual starting date and duration of this work may be
adjusted if inclement weather or other unforeseen delays occur. Dial 511
or log on to 511.ky.gov for the latest
in traffic and travel information in the Commonwealth of Kentucky. You
can also get traffic information for the District 5 counties at www.facebook.com/KYTCDistrict5.